Study of the Ten Thousand Tons Level Fe-Based Amorphous Alloy Raw Material Industrialization |
ZHANG Feng-quan1, WANG Ru-wu1, 2, ZHANG Zhong-yu3 |
1. National Engineering Research Center for Silicon Steel, Wuhan 430080, Hubei,China 2. School of Science Wuhan University of Science and Technology, Wuhan 430081, Hubei,China 3. South Continuous Casting Engineer Co. Ltd, Nanchang 330200,Jiangxi,China |
|
|
Abstract The bottom blowing electroslag induction furnace and the vacuum induction ladle refining furnace were studied for ten thousand tons level Fe-based amorphous alloy raw material supply problems. The results show that using 2 sets of 2 tons level bottom blowing electroslag induction furnace for melting and refining, 1 sets of 4 tons level vacuum induction ladle refining furnace for secondary refining can ensure the composition precision of Fe-based amorphous alloy and its production capacity can meet the ten thousand tons level Fe-based amorphous alloy production.
|
Received: 25 November 2013
Published: 11 March 2014
|
|
|
|
[2] |
中国电工钢产业发展与研究,中国金属学会电工钢分会,2012。
|
[4] |
国家863支撑项目-节能型电机用高硅电工钢的工发,双辊薄带连铸冶炼设备-三工位真空感应钢包精炼炉开发。
|
[1] |
张淑兰,王建,陈非非,王立军.高饱和磁感应强度铁基非晶、纳米晶研究进展[J].金属功能材料, 2010, 17(6):73-77
|
[3] |
国家863支撑项目-节能型电机用高硅电工钢的工发,双辊薄带连铸冶炼设备-底吹电渣感应炉研究开发。
|
|
|
|